June 23, 2017

The green complex on the 6th hole has been shaped.  The rock wall on the 7th green has been installed and work has started on the 8th green rock wall.  Additional drainage has been installed on the 12th hole to improve wet conditions and the coquina has been placed in the waste bunker.  Capillary concrete has been in stalled in the bunkers on 12, 13, 14, 1, 2 & 9.  The 16th green complex has been shaped.  Asphalt cart paths will be installed on 12, 13, 14, 1, 2 & 10 beginning Monday morning.  Sod is scheduled for delivery on Wednesday for around the bunkers on the first 6 holes.  Lots of work happening all over the golf course.  Amazing how much work can be accomplished when Mother Nature cooperates, 19 inches of rain in 21 days since June 1st.