About Me

Friday, May 19, 2017

May 19, 2017

Work continues.  Unfortunately the bulldozer hit the 6" mainline on the 14th hole late Thursday.  This was quickly repaired Friday morning and the system was pressurized.  Almost all of the bury pits have been dug and stripping of the tee/green complexes should be wrapped up late next week.  Shaper will finish up the 14th features Saturday and on Monday will move to the 9th hole.