Busy day of renovation on the golf course.  The lead shaper did some work on the 14th fairway/rough areas and then moved back to the 12 hole to work on the new features.  The bunkers on the left side of the 12th hole were removed and then began to shape the waste bunker area.  Once completed he will move over to the right side and remove the bunker and shape.  The finish shaper started today and he did his initial float of the greens wells on 12, 13 & 14.  Once these were completed he began to shape and level the 12 tee boxes.  Elsewhere, bury pits were being dug.  Strippings on 1 & 9 greens and tee complexes were removed and put in the bury pits.  A few photos of the work on 12 & 14.

 
Work on the left side of #14

The 12th green well being floated

 
Shaping the waste bunker on the 12th

  
Shaping and leveling on the 12th tee boxes